10th & 11th Street Viaduct Major Investment Study

10th & 11th Street Viaduct Major Investment Study Skip to main content

Schedule

Project Timeline

  • Phase 1 (Baseline Conditions and Visioning) - August 2024 to December 2024
  • Phase 2 (Concept Development) - January 2025 to April 2025
  • Phase 3 (Build Alternatives, refinement, Evaluation, and Recommendations) - May 2025 to October 2025
  • Study Report - September 2025 to December 2025
  • Environmental Screening - April 2024 to December 2025
  • Stakeholder and Public Meeting #1 - December 2024
  • Stakeholder and Public Meeting #2 - April 2025
  • Stakeholder and Public Meeting #3 - October 2025