Schedule
Project Timeline
- Phase 1 (Baseline Conditions and Visioning) - August 2024 to December 2024
- Phase 2 (Concept Development) - January 2025 to April 2025
- Phase 3 (Build Alternatives, refinement, Evaluation, and Recommendations) - May 2025 to October 2025
- Study Report - September 2025 to December 2025
- Environmental Screening - April 2024 to December 2025
- Stakeholder and Public Meeting #1 - December 2024
- Stakeholder and Public Meeting #2 - April 2025
- Stakeholder and Public Meeting #3 - October 2025
Schedule Legend
- Baseline Conditions and Visioning
- Concept Development
- Build Alternatives, refinement, Evaluation, and Recommendations